The daily report must contain all the elements applicable to the declared day including, in particular,(1) the completion authorization number;
(2) the name of the drilling installation;
(3) the number of persons on board;
(4) a description, in chronological order, of the work carried out and the time required for carrying out each step of the work;
(5) the name of the enterprises that carry out the completion work;
(6) a summary of the meteorological conditions;
(7) the result of all the pressure and leak tests, including their duration and the initial and final test pressures;
(8) the operating condition of the blowout prevention system;
(9) the well logs carried out;
(10) the type of seals installed and the installation depths;
(11) the technical details of the perforations, in particular, the number, type and intervals;
(12) if applicable, the technical details of the completion by chemical stimulation, in particular, the intervals, concentrations and volumes of acids and additives injected, the volume of flow-back water and the flows, and the injection pressures;
(13) the composition, concentration and detailed assessment of all the products identified in the technical program that are stored or used on the activity site;
(14) the number, interval, volume of fluid, injection rate and pressure and a summary of the results of each injectivity test;
(15) the volume and composition of the gas used, released, incinerated or burned at the flare;
(16) the operational problems encountered and the corrective measures taken or planned;
(17) the indication of any event that disrupted the progress of the work;
(18) the abnormal meteorological conditions that caused an operation delay, in particular, due to(a) visibility;
(b) temperature variation;
(c) wind speed or direction;
(d) the height, period and direction of the waves and swells;
(e) the size, distance and direction of ice;
(f) icing; and
(g) rolling, pitch and vertical motion of the vessel or drilling installation;
(19) if applicable, the size, distance and direction of ice;
(20) the indication of any temporary completion work interruption and the procedure followed to secure the well; and
(21) any other information deemed necessary by the Minister.